Layout Design Development By Using Direct Supply Method
Keywords:
Work Measurement, Time Study, MudaAbstract
The aim of this project is to study the layout design at sub – assembly instrument panel area of a company. The company is an industry for automotive products. In this study, it was found the at sub – assembly instrument panel area in the company was facing problems with achieve takt time 5.8 min per production. In order to overcome these problems, the workforce productivity was measured using work measurement method. The objectives of this study were to study the current layout design at instrument panel area, to purpose a new design layout and to optimize the utilization of the space in sub – assembly instrument panel area. Time study was used as the method for work measurement. New layout design was designed to increase the daily production in line and eliminate muda during handling the processes.