Refurbishment SSD Testers Building 1 On Production Line At New Site
Keywords:
Refurbishment, SSD, Production, Layout Design, Lead time and Capacity PlanningAbstract
This paper presents the result of a comprehensive refurbishment SSD Testers on production line at new site of Micron Memory Malaysia. The inadequate space in Solid State Drive (SSD) manufacturing line at first site to support new testers for additional New Incoming Product (NPI) is the core issue for this research. The best alternative is to loan temporary space to the other product assembly line to run new testers activities at second site which is the new Building 1. The findings depict an overall version of specific layout, testers' implementation lead time analysis and the impact latest testers quantity construct the balancing of capacity planning in operation. Based on this study able to capture on how the space has been utilized for allocated the SSD testers to support flourishing of upcoming demands.